GS E&C Asked to Leave Sangdaewon 2 District Site…Revocation of Preferred Bidder Status and Bid Deposit Forfeiture Threatened
English translation of the original Korean report. Images and source documents may contain Korean text.

Court Maintains Suspension of Contractor Selection Resolution…GS E&C Notified to Halt Promotional Activities Following Association Chair’s Dismissal
Bid Deposit Forfeiture Notice Also Issued in April…GS E&C Maintains Its Existing Preferred Bidder Status Remains Intact
Just over five months after disclosing its selection as contractor for the approximately 1.9218 trillion won redevelopment project in Sangdaewon 2 District, Seongnam, Gyeonggi Province, GS E&C was asked by the redevelopment association to leave the project site and cease promotional activities.
Following the change in association chair, the new leadership also warned that GS E&C’s bid deposit could be forfeited and its preferred bidder status revoked. With a notice of forfeiture concerning the 30 billion won bid deposit having also been issued in April, the dispute over construction rights has once again extended to the deposit issue.
According to a review of reports by Edaily and the redevelopment industry on the 18th, the new leadership of the Sangdaewon 2 District Housing Redevelopment and Improvement Project Association sent an official letter to GS E&C on the 16th, requesting that the company leave the project site and cease individual promotional activities targeting association members. The letter also specifically called for an end to efforts to encourage visits to promotional galleries, publicity through social networking services (SNS), individual visits and telephone calls to association members, and the distribution of leaflets.
The association alleged that GS E&C had violated bidding guidelines and said it would initiate procedures to revoke the company’s preferred bidder status, forfeit its bid deposit and disqualify it from participating in bids. However, whether any violation occurred and whether sanctions will actually be imposed have not been determined. This does not mean that the bid deposit has already been forfeited.
This is not the first time the issue of forfeiting GS E&C’s bid deposit has been raised. On April 10, the emergency committee, which was then seeking the dismissal of the association chair, alleged that GS E&C had colluded with the leadership that had been dismissed at the time to disrupt the bidding process. The committee notified GS E&C that its 30 billion won bid deposit would be forfeited. However, the court suspended the effect of the resolution dismissing the association chair that same day, allowing the previous chair to return to office. It has not been confirmed whether the deposit forfeiture was actually carried out at the time.
■ Court Blocks Contractor Change After GS E&C’s Selection Disclosure…Association Chair’s Dismissal Brings Another Turning Point
On June 1, GS E&C disclosed to the Korea Exchange (KRX) that it had been selected as the contractor for the Sangdaewon 2 District redevelopment project. The disclosure followed the approval of proposals to terminate the contract with existing contractor DL E&C and select GS E&C at the association’s general meeting on May 30. The disclosed estimated construction contract value was approximately 1.9218 trillion won (excluding value-added tax), and the project comprised 4,885 housing units. However, GS E&C stated in the disclosure that key terms, including the contract amount and construction period, had not been finalized pending execution of the main contract.
However, on July 31, the Seongnam Branch of Suwon District Court suspended the effect of the general meeting resolution concerning the contractor change and provisionally recognized DL E&C’s status as the contractor. Of the 2,268 association members, at least 1,135 were required to attend in person, but the court recognized only 1,134, leaving a shortfall of one person. GS E&C also announced the court’s suspension order through a corrective disclosure that day. The decision is distinct from a final judgment on the merits of the main lawsuit.
The association challenged the court’s decision, but the existing injunction was upheld on October 28. Subsequently, at an extraordinary general meeting convened by the emergency committee on November 14, motions to dismiss the existing association chair, who had pursued a contractor change to GS E&C, and two directors were approved. Of the 1,190 participants in the vote, 1,173 (98.6%) supported the motion to dismiss the chair, who has since become the former chair. A new leadership structure headed by an acting association chair was subsequently established.
GS E&C has maintained that its preferred bidder status remains intact even after the court’s suspension order. In a NewsPIM report on the 5th, a GS E&C representative explained that unverified information was spreading through unofficial channels, prompting inquiries from association members, and that the company was seeking to operate a promotional gallery to provide accurate information. However, no new official position from GS E&C has been confirmed regarding the new leadership’s request on the 16th that it leave the project site and halt promotional activities.
On the same day that it asked GS E&C to leave the project site, the new leadership approved previously deferred demolition work at a Baptist church and outer retaining-wall construction for Complex 2 on the side facing Seongnam Xi Apartments, and requested that DL E&C, the existing contractor, resume the work. It also announced the postponement of the extraordinary general meetings scheduled for November 15 and 28 that had been convened by the former association chair, and notified relevant authorities, including Seongnam City and the Korea Housing & Urban Guarantee Corporation (HUG), of the dismissal of the association chair and directors.